Aishwaryam Hamara Construction Site's Latest Work Progress

1) BUILDING : A-7
    STATUS : 1ST SLAB CONCRETING DONE, ABOVE 1ST 
    SLAB COLUMN 90% DONE. 2ND SLAB SHUTTERING
    & STEEL ERECTION WORK IN PROGRESS. 


 2) BUILDING : A-8
     STATUS : 1ST SLAB CONCRETING DONE
     ABOVE 1ST SLAB COLUMN 70% DONE. 


3) BUILDING : A-9
    STATUS : 1ST SLAB CONCRETING DONE.


4) BUILDING : A-10
    STATUS : 1ST SLAB IS READY TO CONCRETING.


5) BUILDING : A-11
    STATUS : 1ST SLAB SHUTTERING & STEEL
    ERECTION 70% DONE.


6) BUILDING : A-12
    STATUS : 1ST SLAB SHUTTERING & STEEL 
    ERECTION WORK IN PROGRESS.